PESCO serves the largest geographic area of any DISCO in mainland Pakistan — covering almost all of Khyber Pakhtunkhwa province. Track your ENC application on the central portal using your Tracking ID or CNIC.

  • Covers most of Khyber Pakhtunkhwa province
  • Track with Tracking ID or CNIC on enc.com.pk
  • Quote Tracking ID when calling 091-111-786-786 for updates
  • Track on enc.com.pk
KPK
Province served
15–30
Days processing
118
PESCO helpline

PESCO coverage

KPK's Primary Distribution Company

PESCO is the backbone electricity distributor for Khyber Pakhtunkhwa, serving both urban centres like Peshawar and Mardan and remote rural districts. Given the province's complex terrain, applications in mountainous areas may require additional time for the field survey and service line extension work.

Peshawar circle

Peshawar, Charsadda, Nowshera, Swabi.

Mardan circle

Mardan, Buner, Malakand, Swat.

Kohat circle

Kohat, Karak, Hangu, Orakzai (merged).

DI Khan circle

Bannu, Lakki Marwat, Tank, DI Khan, South Waziristan (merged).

Districts served

PESCO Service Area

PESCO distributes electricity across almost all of Khyber Pakhtunkhwa — from the provincial capital Peshawar to the remoter districts of the province. Hazara Division is served by HAZECO, not PESCO.

PeshawarMardanSwatCharsaddaNowsheraSwabiBunerMalakandDir LowerDir UpperKohatKarakHanguBannuLakki MarwatTankDera Ismail KhanSouth Waziristan (merged)

Hazara Division (Abbottabad, Haripur, Mansehra, Battagram) is served by HAZECO, not PESCO. Merged tribal districts are served by TESCO.

Application stages

Your PESCO Application Stages

All PESCO ENC applications follow these 7 stages. If no change after 10–15 working days, call 091-111-786-786 with your Tracking ID.

01

Submitted

Application received and queued for DISCO review.

Await SMS with your Tracking ID.

02

Under Review

DISCO is verifying your documents for completeness.

Check mobile for any correction requests.

03

Inspection Scheduled

Field team assigned to survey your premises.

Ensure premises access on the scheduled date.

04

Inspection Completed

Site verified, distances measured, wiring checked.

Await demand notice (2–5 working days).

05

Demand Notice Issued

Official payment voucher with all charges is ready.

Pay at designated bank and upload receipt on portal.

06

Payment Received

Payment verified. Meter installation being scheduled.

Ensure someone available at premises for installation.

07

Energised

Meter installed. Your connection is live.

Collect your consumer number from the DISCO.

Contact PESCO

PESCO Helplines

National helpline

118

PESCO helpline

111-000-128

Peshawar HQ

091-9212028

FAQs

PESCO Application Tracking FAQs

How do I track a PESCO new connection application?

Go to enc.com.pk, click Track, select PESCO, and enter your 11-digit Tracking ID or 13-digit CNIC without dashes.

My PESCO application has been stuck for over 15 working days. What should I do?

Call PESCO's helpline at 091-111-786-786 and quote your Tracking ID. For formal escalation, contact NEPRA at 051-9207200 or file a complaint at nepra.org.pk.

Does PESCO cover Abbottabad and Haripur?

No. Abbottabad, Haripur, Mansehra, and Battagram fall under HAZECO (Hazara Electric Supply Company), not PESCO.

What is PESCO's main contact number?

PESCO's main contact numbers are 111-000-128 and 091-9212028. The universal electricity helpline 118 also connects to PESCO.

How long does a PESCO domestic connection take in rural areas?

Urban areas typically take 15–30 days. In mountainous or remote areas, terrain challenges for service line extensions may add to the timeline. Call 118 if you exceed 30 days.

My PESCO documents were rejected. What do I do?

The ENC portal shows the reason for rejection. Upload the corrected or missing documents through the same portal — no need to reapply.